July 9, 2026
July marks the halfway point in renovating The 411. We started in February and are on track to complete in December.
Things are shaping up inside! We’ve completed about 75% of interior architectural wall framing and some finishes are starting to go in. The curtainwall is going up along the west elevation moving to the south elevation.
The ComEd transformer pad has been set and we will soon start boring to the new electrical pole. Then we will be ready for ComEd to start pulling their cables. Getting on ComEd’s schedule to bring power to the building is a pivotal moment in the project.